Autonomous Haulage Works

Completed:  2020

Project Value:  Ongoing

 

Construction of haul roads, fuel farms, pads and other infrastructure to support the roll-out of autonomous trucks at a major coal mine.

 

Fill material dumped out by the mine’s pre-strip fleet and construction carried out in approximately 1m lifts.
D11 dozers utilized for bulk pushing and track rolling
Tractor-drawn Impact Roller for deep compaction of existing subgrade and rubblisation of fill material
Cat 825 compactor for fine compaction of running surface
773 and Scraper watercarts for fill-conditioning
Cat 16M grader with GPS for trimming and shaping of the running surface
GPS excavators trimming